Radiant Heat works well with wood floors as long as you follow a few simple guidelines:
-If heat is in a slab, the slab should be in place for 60 days.
-Heat should be turned on for at least 30 to 60 days before plywood or flooring is layed over slab.
-If plywood is layed, plywood should be down for at least 2 more weeks before flooring.
-Flooring should be layed out (or" Racked") 2 to 3 days before nailing or gluing floor down.